Dept. of Trans. PROGRESS Serial No. Contract No. 15-260-10-28 06-0S5904 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 18% Location: Federal Project: 06-TUL-198-R14.6 NONE Progress payment No. 001 Payment period ending: 09-20-15 BUGLER CONSTRUCTION 4847 HOPYARD RD.SUITE 4 NO.39 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,050.00 4,050.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,050.00 4,050.00 5. Mobilization 6. Total Work Completed 4,050.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,050.00 4,050.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,050.00