Dept. of Trans. PROGRESS Serial No. Contract No. 19-017-13-17 06-0S6104 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 89% Location: Federal Project: 06-KER-0-0.0 NONE Progress payment No. 016 Payment period ending: 01-20-19 STURGEON ELECTRIC CALIFORNIA LLC 13501 BENSON AVENUE CHINO CA 91710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,929,528.14 467,382.68 2. a. Extra Work 75,122.46 0.00 b. Adustment Comp. -55,737.69 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,948,912.91 467,382.68 5. Mobilization 1,200,000.00 0.00 6. Total Work Completed 10,148,912.91 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,148,912.91 467,382.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 467,382.68