Dept. of Trans. PROGRESS Serial No. Contract No. 16-053-09-54 06-0S7404 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 17% Location: Federal Project: 06-FRE-0-0.0 NHP-000C(401) 06-TUL-0-0.0 Progress payment No. 003 Payment period ending: 02-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614-5706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 284,593.50 282,733.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 148,184.08 -94,441.94 4. Earned Subject to Retention 432,777.58 188,291.56 5. Mobilization 64,600.00 13,600.00 6. Total Work Completed 349,193.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 497,377.58 201,891.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 201,891.56