Dept. of Trans. PROGRESS Serial No. Contract No. 16-078-14-43 06-0S7404 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 36% Location: Federal Project: 06-FRE-0-0.0 NHP-000C(401) 06-TUL-0-0.0 Progress payment No. 004 Payment period ending: 03-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614-5706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 537,245.93 252,652.43 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 95,278.89 -52,905.19 4. Earned Subject to Retention 632,524.82 199,747.24 5. Mobilization 64,600.00 0.00 6. Total Work Completed 601,845.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 697,124.82 199,747.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 199,747.24