Dept. of Trans. PROGRESS Serial No. Contract No. 16-112-12-42 06-0S7404 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 55% Location: Federal Project: 06-FRE-0-0.0 NHP-000C(401) 06-TUL-0-0.0 Progress payment No. 005 Payment period ending: 04-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614-5706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,056,772.21 519,526.28 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -95,278.89 4. Earned Subject to Retention 1,056,772.21 424,247.39 5. Mobilization 68,000.00 3,400.00 6. Total Work Completed 1,124,772.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,124,772.21 427,647.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 427,647.39