Dept. of Trans. PROGRESS Serial No. Contract No. 23-057-15-08 06-0S8304 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 32% Location: Federal Project: 06-FRE-5-44.4/45.4 ACIM-005-5(155) Progress payment No. 007 Payment period ending: 02-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,365,820.45 367,761.47 2. a. Extra Work 36,916.12 36,916.12 b. Adustment Comp. 3. Materials on Hand 199,983.80 -152,770.00 4. Earned Subject to Retention 4,602,720.37 251,907.59 5. Mobilization 1,045,000.00 0.00 6. Total Work Completed 5,447,736.57 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,647,720.37 261,907.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 261,907.59