Dept. of Trans. PROGRESS Serial No. Contract No. 23-115-11-55 06-0S8304 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 43% Location: Federal Project: 06-FRE-5-44.4/45.4 ACIM-005-5(155) Progress payment No. 009 Payment period ending: 04-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,447,654.04 782,084.68 2. a. Extra Work 36,916.12 0.00 b. Adustment Comp. 3. Materials on Hand 152,770.00 -47,213.80 4. Earned Subject to Retention 5,637,340.16 734,870.88 5. Mobilization 1,100,000.00 55,000.00 6. Total Work Completed 6,584,570.16 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,737,340.16 789,870.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 789,870.88