Dept. of Trans. PROGRESS Serial No. Contract No. 23-207-09-31 06-0S8304 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 64% Location: Federal Project: 06-FRE-5-44.4/45.4 ACIM-005-5(155) Progress payment No. 012 Payment period ending: 07-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,022,272.45 403,832.21 2. a. Extra Work 393,108.71 101,620.19 b. Adustment Comp. 3. Materials on Hand 33,061.72 -152,770.00 4. Earned Subject to Retention 7,448,442.88 352,682.40 5. Mobilization 1,100,000.00 0.00 6. Total Work Completed 8,515,381.16 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,545,442.88 349,682.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 349,682.40