Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-274-16-18 06-0S8304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-5-44.4/45.4 ACIM-005-5(155) Progress payment No. 020 Payment period ending: 05-10-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,363,368.09 0.00 2. a. Extra Work 627,531.76 5,000.00 b. Adustment Comp. -161,831.41 -162,711.79 3. Materials on Hand 4. Earned Subject to Retention 10,829,068.44 -157,711.79 5. Mobilization 1,100,000.00 0.00 6. Total Work Completed 11,929,068.44 7. Deductions -42,728.75 30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,886,339.69 -127,711.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -127,711.79