Dept. of Trans. PROGRESS Serial No. Contract No. 15-352-09-39 06-0S9304 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 51% Location: Federal Project: 06-FRE-0-0.0 NHST-PG 398-E Progress payment No. 002 Payment period ending: 12-20-15 PELAGIC ENGINEERING 3600 HARBOR BLVD. #85 OXNARD CA 93035 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 225,188.30 126,906.46 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 225,188.30 126,906.46 5. Mobilization 6. Total Work Completed 225,188.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 225,188.30 126,906.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,906.46