Dept. of Trans. PROGRESS Serial No. Contract No. 21-172-12-19 06-0T0304 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 37% Location: Federal Project: 06-KER-5 NONE 06-KIN-5-0.0 06-FRE-5-0.0 Progress payment No. 003 Payment period ending: 06-20-21 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 465,360.00 1,640.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 465,360.00 1,640.00 5. Mobilization 41,850.35 0.00 6. Total Work Completed 507,210.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 507,210.35 1,640.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,640.00