Dept. of Trans. PROGRESS Serial No. Contract No. 22-053-10-36 06-0T0304 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 87% Location: Federal Project: 06-KER-5 NONE 06-KIN-5-0.0 06-FRE-5-0.0 Progress payment No. 009 Payment period ending: 02-20-22 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 868,967.00 1,386.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 868,967.00 1,386.00 5. Mobilization 44,053.00 0.00 6. Total Work Completed 913,020.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 913,020.00 1,386.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,386.00