Dept. of Trans. PROGRESS Serial No. Contract No. 20-141-12-52 06-0T20U4 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 72% Location: Federal Project: 06-KER-99-L0.0/11.2 B1NH-P099(636) Progress payment No. 014 Payment period ending: 05-20-20 GRIFFITH VANGUARD JOINT VENTURE 1128 CARRIER PKWY AVENUE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,903,974.21 5,779,250.00 2. a. Extra Work 2,443,105.40 0.00 b. Adustment Comp. 10,864.11 0.00 3. Materials on Hand 480,600.00 466,801.08 4. Earned Subject to Retention 33,838,543.72 6,246,051.08 5. Mobilization 5,800,000.00 290,000.00 6. Total Work Completed 39,157,943.72 7. Deductions -152,804.12 -16,562.51 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 39,485,739.60 6,519,488.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,519,488.57