Dept. of Trans. PROGRESS Serial No. Contract No. 19-081-11-07 06-0T2904 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 9% Location: Federal Project: 06-KIN-198-R8.3/R19.4 ACNH-P198(80) Progress payment No. 001 Payment period ending: 03-20-19 BOSCO CONSTRUCTORS INC 21353 MAYALL ST CHATSWORTH CA 91311 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 175,812.69 175,812.69 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 175,812.69 175,812.69 5. Mobilization 6. Total Work Completed 175,812.69 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 175,812.69 175,812.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 175,812.69