Dept. of Trans. PROGRESS Serial No. Contract No. 16-231-15-08 06-0T3304 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 45% Location: Federal Project: 06-KER-99-0.0/56.7 NONE 06-TUL-99-0.2/7.9 Progress payment No. 002 Payment period ending: 08-20-16 BENTANCOURT BROS CONSTRUCTION INC 5933 NORTHFRONT RD LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 162,088.00 143,753.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 162,088.00 143,753.00 5. Mobilization 6. Total Work Completed 162,088.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 162,088.00 143,753.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,753.00