Dept. of Trans. FINAL Serial No. Contract No. 17-012-14-28 06-0T3304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-99-0.0/56.7 NONE 06-TUL-99-0.2/7.9 Progress payment No. 007 Payment period ending: 11-15-16 BENTANCOURT BROS CONSTRUCTION INC 8015 WEST 11TH ST TRACY CA 95304 9303 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 706,049.90 0.00 2. a. Extra Work 17,955.13 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 724,005.03 0.00 5. Mobilization 6. Total Work Completed 724,005.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 724,005.03 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00