Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-14-23 06-0T3504 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 11% Location: Federal Project: 06-TUL-137-16.5/16.6 ACNH-P137(10) Progress payment No. 002 Payment period ending: 04-20-22 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 261,992.86 253,637.86 2. a. Extra Work 7,033.77 7,033.77 b. Adustment Comp. 3. Materials on Hand 0.00 -241,977.21 4. Earned Subject to Retention 269,026.63 18,694.42 5. Mobilization 159,000.00 0.00 6. Total Work Completed 428,026.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 428,026.63 18,694.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,694.42