Dept. of Trans. PROGRESS Serial No. Contract No. 19-081-11-06 06-0T3604 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 63% Location: Federal Project: 06-FRE-99-R0.0/14.9 ACNH-P099(621) 06-TUL-99-R53.8/53.9 Progress payment No. 004 Payment period ending: 03-20-19 DAWSON-MAULDIN CONSTRUCTION INC PO BOX 8397 HUNTINGTON BEACH CA 92615 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,500,500.43 790,831.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,500,500.43 790,831.40 5. Mobilization 216,050.00 10,802.50 6. Total Work Completed 1,716,550.43 7. Deductions -531,283.63 -180,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,185,266.80 621,633.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 621,633.90