Dept. of Trans. PROGRESS Serial No. Contract No. 17-354-15-06 06-0T5104 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 68% Location: Federal Project: 06-KIN-198-R18.4 SNHG-P198(75) Progress payment No. 003 Payment period ending: 12-20-17 CAL ELECTRO INC 3710 ELECTRO WAY REDDING CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 284,527.15 99,886.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 284,527.15 99,886.80 5. Mobilization 36,100.00 0.00 6. Total Work Completed 320,627.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 320,627.15 99,886.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 99,886.80