Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-10-23 06-0T6104 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 24% Location: Federal Project: 06-KIN-5-16.6/26.7 NHPI-054(196) 309E Progress payment No. 001 Payment period ending: 09-20-16 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 67,716.89 67,716.89 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 67,716.89 67,716.89 5. Mobilization 6. Total Work Completed 67,716.89 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 67,716.89 67,716.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,716.89