Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-320-15-00 06-0T7604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-TUL-216-11.7/19.3 NONE Progress payment No. 006 Payment period ending: 10-13-17 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,270,959.35 -3,300.00 2. a. Extra Work 13,617.05 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,284,576.40 -3,300.00 5. Mobilization 6. Total Work Completed 1,284,576.40 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,274,576.40 -3,300.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -3,300.00