Dept. of Trans. FINAL Serial No. Contract No. 18-099-11-22 06-0T8104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KIN-33-12.0/19.0 ACST-S033(85) 06-FRE-33-0.0/10.7 Progress payment No. 005 Payment period ending: 08-21-17 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,298,326.71 0.00 2. a. Extra Work 65,417.13 8,233.19 b. Adustment Comp. 65,907.05 65,907.05 3. Materials on Hand 4. Earned Subject to Retention 3,429,650.89 74,140.24 5. Mobilization 6. Total Work Completed 3,429,650.89 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,429,650.89 74,140.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,140.24