Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-069-15-07 06-0U0004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-33-70.6/76.0 NONE 06-KER-58-27.8/76.0 Progress payment No. 005 Payment period ending: 02-20-25 BUGLER CONSTRUCTION INC 4847 HOPYARD RD #4 #395 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,510,928.00 317,925.00 2. a. Extra Work 61,947.38 55,000.00 b. Adustment Comp. -279,403.87 -274,403.87 3. Materials on Hand 4. Earned Subject to Retention 1,293,471.51 98,521.13 5. Mobilization 170,000.00 0.00 6. Total Work Completed 1,463,471.51 7. Deductions -49,276.00 -49,276.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,414,195.51 49,245.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,245.13