Dept. of Trans. PROGRESS Serial No. Contract No. 21-297-13-47 06-0U0404 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 79% Location: Federal Project: 06-TUL-63-0.0 SSTG-X107(20) 06-TUL-137-0.0 Progress payment No. 004 Payment period ending: 10-20-21 BUSH ENGINEERING INC PO BOX 1323 HANFORD CA 93232 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 627,324.83 279,185.13 2. a. Extra Work 15,384.62 15,384.62 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 642,709.45 294,569.75 5. Mobilization 75,800.00 3,790.00 6. Total Work Completed 718,509.45 7. Deductions -2,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 716,509.45 297,359.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,359.75