Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-253-11-02 06-0U0804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-5-21.0/31.0 B1IM-005-5(151) Progress payment No. 006 Payment period ending: 08-27-19 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,998,527.66 284,617.67 2. a. Extra Work b. Adustment Comp. -150,174.25 -150,174.25 3. Materials on Hand 4. Earned Subject to Retention 10,848,353.41 134,443.42 5. Mobilization 1,220,000.00 0.00 6. Total Work Completed 12,068,353.41 7. Deductions -25,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,043,353.41 114,443.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,443.42