Dept. of Trans. PROGRESS Serial No. Contract No. 19-323-14-11 06-0U09U4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 98% Location: Federal Project: 06-FRE-168-R36.0/65.9 B1ST-S168(64) Progress payment No. 013 Payment period ending: 11-20-19 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,988,972.45 554,098.75 2. a. Extra Work 349,684.98 125,034.12 b. Adustment Comp. -13,420.26 -15,520.50 3. Materials on Hand 4. Earned Subject to Retention 14,325,237.17 663,612.37 5. Mobilization 427,000.00 0.00 6. Total Work Completed 14,752,237.17 7. Deductions -462,358.07 -105,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,289,879.10 558,612.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 558,612.37