Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-330-11-59 06-0U09U4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-168-R36.0/65.9 B1ST-S168(64) Progress payment No. 014 Payment period ending: 11-20-19 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,063,778.45 74,806.00 2. a. Extra Work 458,934.14 109,249.16 b. Adustment Comp. -13,420.26 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,509,292.33 184,055.16 5. Mobilization 427,000.00 0.00 6. Total Work Completed 14,936,292.33 7. Deductions -239,227.32 223,130.75 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,697,065.01 407,185.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 407,185.91