Dept. of Trans. SEMI-FINAL Serial No. Contract No. 18-044-13-55 06-0U2104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-0-0.0 NONE Progress payment No. 005 Payment period ending: 10-12-17 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 317,694.96 0.00 2. a. Extra Work b. Adustment Comp. 3,000.40 0.00 3. Materials on Hand 4. Earned Subject to Retention 320,695.36 0.00 5. Mobilization 6. Total Work Completed 320,695.36 7. Deductions -11,932.62 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 308,762.74 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00