Dept. of Trans. PROGRESS Serial No. Contract No. 21-025-14-13 06-0U2304 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 25% Location: Federal Project: 06-FRE-99-0.0 NONE 06-MAD-99-0.0 06-TUL-99-0.0 Progress payment No. 001 Payment period ending: 01-20-21 KOCH & KOCH INC 578 SUTTON WAY #333 GRASS VALLEY CA 95945 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 70,800.00 70,800.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 70,800.00 70,800.00 5. Mobilization 6. Total Work Completed 70,800.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 70,800.00 70,800.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,800.00