Dept. of Trans. PROGRESS Serial No. Contract No. 23-052-13-54 06-0U2804 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 60% Location: Federal Project: 06-TUL-245-1.4/1.4 ACST-S245(1) 06-TUL-245-4.2/4.2 Progress payment No. 008 Payment period ending: 02-20-23 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,371,287.50 -1,767,556.50 2. a. Extra Work 2,534,817.34 2,329,710.48 b. Adustment Comp. 78,964.01 78,602.01 3. Materials on Hand 0.00 -302,075.18 4. Earned Subject to Retention 7,985,068.85 338,680.81 5. Mobilization 1,030,000.00 0.00 6. Total Work Completed 9,015,068.85 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,015,068.85 340,680.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 340,680.81