Dept. of Trans. PROGRESS Serial No. Contract No. 25-199-15-00 06-0U4214 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 8% Location: Federal Project: 06-FRE-99-R4.9/7.2 NONE 06-FRE-99-10.1/11.6 Progress payment No. 004 Payment period ending: 07-20-25 WABO LANDSCAPE & CONSTRUCTION INC 726 ALFRED NOBEL DR HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 655,120.00 372,595.00 2. a. Extra Work 48,831.12 48,831.12 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 703,951.12 421,426.12 5. Mobilization 164,350.00 34,600.00 6. Total Work Completed 868,301.12 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 858,301.12 456,026.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 456,026.12