Dept. of Trans. PROGRESS Serial No. Contract No. 22-172-14-35 06-0U4504 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 06-FRE-168-18.6/T25.5 NONE Progress payment No. 012 Payment period ending: 06-20-22 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,198,915.82 0.00 2. a. Extra Work b. Adustment Comp. 361,532.51 -32,529.27 3. Materials on Hand 4. Earned Subject to Retention 3,560,448.33 -32,529.27 5. Mobilization 385,000.00 0.00 6. Total Work Completed 3,945,448.33 7. Deductions -309,298.50 247,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,636,149.83 214,970.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 214,970.73