Dept. of Trans. PROGRESS Serial No. Contract No. 25-143-12-32 06-0U8804 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 63% Location: Federal Project: 06-TUL-99-26.3/27.6 ILDL-6206(33) Progress payment No. 020 Payment period ending: 05-20-25 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,381,976.44 1,248,174.36 2. a. Extra Work 112,268.96 33,094.90 b. Adustment Comp. 3. Materials on Hand 72,102.02 72,102.02 4. Earned Subject to Retention 15,566,347.42 1,353,371.28 5. Mobilization 3,325,000.00 0.00 6. Total Work Completed 18,819,245.40 7. Deductions -80,096.04 385,359.47 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,811,251.38 1,738,730.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,738,730.75