Dept. of Trans. PROGRESS Serial No. Contract No. 26-005-14-25 06-0U8804 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 89% Location: Federal Project: 06-TUL-99-26.3/27.6 ILDL-6206(33) Progress payment No. 030 Payment period ending: 12-20-25 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,016,029.75 851,029.46 2. a. Extra Work 248,081.80 27,200.00 b. Adustment Comp. -147,253.63 -147,253.63 3. Materials on Hand 4. Earned Subject to Retention 29,116,857.92 730,975.83 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 32,616,857.92 7. Deductions -250,510.55 -172,757.37 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,366,347.37 558,218.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 558,218.46