Dept. of Trans. PROGRESS Serial No. Contract No. 19-233-10-32 06-0U9504 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 47% Location: Federal Project: 06-TUL-190-48.5/56.6 NONE 06-FRE-168-R33.0/65.9 06-MAD-41-29.0/45.7 Progress payment No. 006 Payment period ending: 08-20-19 SIERRA MOUNTAIN CONSTRUCTION INC 13919 MONO WAY SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,426,725.00 1,382,800.00 2. a. Extra Work 405,186.14 345,427.14 b. Adustment Comp. 25,029.80 25,029.80 3. Materials on Hand 4. Earned Subject to Retention 4,856,940.94 1,753,256.94 5. Mobilization 400,000.00 0.00 6. Total Work Completed 5,256,940.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,256,940.94 1,753,256.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,753,256.94