Dept. of Trans. PROGRESS Serial No. Contract No. 23-082-09-52 06-0V2804 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 90% Location: Federal Project: 06-KER-184-L0.9/L1.1 SSTG-P184(16) Progress payment No. 005 Payment period ending: 03-20-23 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 703,721.50 220,995.82 2. a. Extra Work 68,171.07 9,649.05 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 771,892.57 230,644.87 5. Mobilization 270,750.00 57,000.00 6. Total Work Completed 1,042,642.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,042,642.57 287,644.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 287,644.87