Dept. of Trans. PROGRESS Serial No. Contract No. 19-165-11-05 06-0V4604 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 78% Location: Federal Project: 06-FRE-99-R0.4/30.5 NONE Progress payment No. 006 Payment period ending: 06-20-19 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,105,934.04 1,045,007.38 2. a. Extra Work 29,477.20 1,000.00 b. Adustment Comp. 818.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,136,230.09 1,046,007.38 5. Mobilization 474,965.00 0.00 6. Total Work Completed 4,611,195.09 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,601,195.09 1,046,007.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,046,007.38