Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-275-11-10 06-0V5004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-5-0.0/10.0 ACIM-005-5(150) Progress payment No. 004 Payment period ending: 09-21-18 TELFER PAVEMENT TECHNOLOGIES LLC 4522 PARKER AVE BLDG 700 #350 MCCLELLAN CA 95652 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,601,544.66 -155,812.72 2. a. Extra Work 4,500.00 0.00 b. Adustment Comp. 84,404.31 36,854.31 3. Materials on Hand 4. Earned Subject to Retention 3,690,448.97 -118,958.41 5. Mobilization 280,000.00 0.00 6. Total Work Completed 3,970,448.97 7. Deductions -36,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,934,448.97 -148,958.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -148,958.41