Dept. of Trans. PROGRESS Serial No. Contract No. 20-296-11-36 06-0V7504 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 76% Location: Federal Project: 06-FRE-41-R21.0/R31.0 NONE Progress payment No. 008 Payment period ending: 10-20-20 CLEAN CUT LANDSCAPE INCORPORATED 1865 HERNDON AVE #K591 CLOVIS CA 93611 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 353,554.09 14,557.41 2. a. Extra Work 215,786.33 44,625.21 b. Adustment Comp. 3. Materials on Hand 13,883.77 -17,397.71 4. Earned Subject to Retention 583,224.19 41,784.91 5. Mobilization 95,608.00 0.00 6. Total Work Completed 664,948.42 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 676,832.19 41,784.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,784.91