Dept. of Trans. PROGRESS Serial No. Contract No. 20-169-15-53 06-0V9104 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 27% Location: Federal Project: 06-FRE-99-0.0 NONE Progress payment No. 004 Payment period ending: 06-20-20 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,989,004.99 264,917.50 2. a. Extra Work b. Adustment Comp. -2,672.46 -2,672.46 3. Materials on Hand 4. Earned Subject to Retention 1,986,332.53 262,245.04 5. Mobilization 399,999.00 19,999.95 6. Total Work Completed 2,386,331.53 7. Deductions -275,038.90 -50,001.95 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,111,292.63 232,243.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 232,243.04