Dept. of Trans. PROGRESS Serial No. Contract No. 20-357-13-47 06-0V9104 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 47% Location: Federal Project: 06-FRE-99-0.0 NONE Progress payment No. 009 Payment period ending: 12-20-20 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,519,438.10 920,465.00 2. a. Extra Work 12,403.86 12,403.86 b. Adustment Comp. -19,906.26 -16,500.00 3. Materials on Hand 0.00 -879,759.65 4. Earned Subject to Retention 3,511,935.70 36,609.21 5. Mobilization 399,999.00 0.00 6. Total Work Completed 3,911,934.70 7. Deductions -85,186.44 -25,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,826,748.26 11,609.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,609.21