Dept. of Trans. PROGRESS Serial No. Contract No. 21-053-08-05 06-0V9104 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 73% Location: Federal Project: 06-FRE-99-0.0 NONE Progress payment No. 011 Payment period ending: 02-20-21 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,609,270.06 19,059.82 2. a. Extra Work 12,403.86 0.00 b. Adustment Comp. -19,906.26 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,601,767.66 19,059.82 5. Mobilization 399,999.00 0.00 6. Total Work Completed 4,001,766.66 7. Deductions -104,716.44 470.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,897,050.22 19,529.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,529.82