Dept. of Trans. PROGRESS Serial No. Contract No. 23-233-13-34 06-0W1704 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 28% Location: Federal Project: 06-FRE-41-R27.4/R28.5 ACNH-P041(602) Progress payment No. 006 Payment period ending: 08-20-23 RNR CONSTRUCTION INC 8589 THYS CT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,613,777.90 883,350.80 2. a. Extra Work b. Adustment Comp. -13,318.21 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,600,459.69 883,350.80 5. Mobilization 1,472,500.00 310,000.00 6. Total Work Completed 5,072,959.69 7. Deductions -48,430.76 -10,195.95 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,024,528.93 1,183,154.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,183,154.85