Dept. of Trans. PROGRESS Serial No. Contract No. 24-085-17-35 06-0W1704 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 62% Location: Federal Project: 06-FRE-41-R27.4/R28.5 ACNH-P041(602) Progress payment No. 013 Payment period ending: 03-20-24 RNR CONSTRUCTION INC 8589 THYS CT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,234,760.40 406,911.50 2. a. Extra Work 40,676.44 0.00 b. Adustment Comp. -13,318.21 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,262,118.63 406,911.50 5. Mobilization 1,550,000.00 0.00 6. Total Work Completed 10,812,118.63 7. Deductions -93,979.75 6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,718,138.88 412,911.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 412,911.50