Dept. of Trans. PROGRESS Serial No. Contract No. 24-144-19-27 06-0W1704 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 67% Location: Federal Project: 06-FRE-41-R27.4/R28.5 ACNH-P041(602) Progress payment No. 015 Payment period ending: 05-20-24 RNR CONSTRUCTION INC 8589 THYS CT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,088,901.40 366,558.50 2. a. Extra Work 110,637.68 25,461.70 b. Adustment Comp. -13,318.21 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,186,220.87 392,020.20 5. Mobilization 1,550,000.00 0.00 6. Total Work Completed 11,736,220.87 7. Deductions -92,479.75 -12,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,643,741.12 379,520.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 379,520.20