Dept. of Trans. PROGRESS Serial No. Contract No. 24-204-11-00 06-0W1704 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 79% Location: Federal Project: 06-FRE-41-R27.4/R28.5 ACNH-P041(602) Progress payment No. 017 Payment period ending: 07-20-24 RNR CONSTRUCTION INC 8589 THYS CT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,220,496.15 795,742.25 2. a. Extra Work 143,519.54 9,702.06 b. Adustment Comp. -13,318.21 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,350,697.48 805,444.31 5. Mobilization 1,550,000.00 0.00 6. Total Work Completed 12,900,697.48 7. Deductions -362,903.89 -260,424.14 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,537,793.59 545,020.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 545,020.17