Dept. of Trans. PROGRESS Serial No. Contract No. 23-080-17-30 06-0W3904 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 50% Location: Federal Project: 06-TUL-63-L8.8/L9.2 NONE 06-TUL-198-R9.2/R9.7 Progress payment No. 004 Payment period ending: 03-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 639,437.72 46,914.05 2. a. Extra Work 67,655.27 10,554.03 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 707,092.99 57,468.08 5. Mobilization 6. Total Work Completed 707,092.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 707,092.99 57,468.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,468.08