Dept. of Trans. PROGRESS Serial No. Contract No. 25-325-16-08 06-0W9104 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 61% Location: Federal Project: 06-TUL-99-27.6/30.6 ACNH-P099(687) Progress payment No. 008 Payment period ending: 11-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,950,889.14 805,073.85 2. a. Extra Work 534,017.21 10,158.73 b. Adustment Comp. -95,929.62 0.00 3. Materials on Hand 648,932.22 648,932.22 4. Earned Subject to Retention 14,037,908.95 1,464,164.80 5. Mobilization 2,100,000.00 0.00 6. Total Work Completed 15,488,976.73 7. Deductions -61,035.10 -42,254.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,076,873.85 1,421,910.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,421,910.80