Dept. of Trans. PROGRESS Serial No. Contract No. 25-354-10-24 06-0W9104 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 63% Location: Federal Project: 06-TUL-99-27.6/30.6 ACNH-P099(687) Progress payment No. 009 Payment period ending: 12-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,201,067.17 250,178.03 2. a. Extra Work 534,017.21 0.00 b. Adustment Comp. -95,929.62 0.00 3. Materials on Hand 848,716.79 199,784.57 4. Earned Subject to Retention 14,487,871.55 449,962.60 5. Mobilization 2,100,000.00 0.00 6. Total Work Completed 15,739,154.76 7. Deductions -61,035.10 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,526,836.45 449,962.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 449,962.60