Dept. of Trans. PROGRESS Serial No. Contract No. 21-141-14-30 06-0X0404 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 52% Location: Federal Project: 06-TUL-65-0.0 SSTG-X107(19) 06-TUL-190-0.0 Progress payment No. 002 Payment period ending: 05-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 808,526.50 364,751.50 2. a. Extra Work 14,565.65 14,565.65 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 823,092.15 379,317.15 5. Mobilization 105,000.00 5,250.00 6. Total Work Completed 928,092.15 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 927,092.15 383,567.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 383,567.15